Construction hours extended for Talley Street school due to heavy rain

Decatur

Construction hours extended for Talley Street school due to heavy rain

City Schools of Decatur Administrative Offices. Photo by Dena Mellick
Share

 

After several days of rainy weather, the construction company developing the future Talley Street Upper Elementary school will work overtime in an effort to complete the project on time, according to an update from the city of Decatur.

Between Jan. 5 and Jan. 11, the company will have extended work hours. The construction schedule will be as follows:

  • Saturday, Jan. 5: construction from 7 a.m. until 5 p.m.
  • Sunday, Jan. 6: construction from 9 a.m. until 5 p.m.
  • Monday, Jan. 7 through Friday, Jan. 11: construction expected all day, with some work days lasting from 3 a.m. until midnight.

The day-long schedule will allow the company to accommodate necessary concrete pours.

Those with any questions or concerns should contact the DEC Director John Maximuk at John.Maximuk@decaturga.com, the city said.

 

Don’t miss the latest news from Decaturish. Join our mailing list!

* indicates required





Decaturish needs your support!

Help us provide you with free, quality local news. Become a Decaturish.com supporter today

To chip in $3 a month, click here.

To chip in $6 a month, click here.

To chip in $60 a year, click here.
* Decaturish.com is not a 501-c-3 organization. Support of Decaturish goes toward our newsgathering efforts. Decaturish does not have a print edition.
close-link